(1) When using the drilling rig to drill, the driver should be placed in the drilling position, so that the front end is against the rock, and the distribution should be careful to let the drilling rig move forward, so that the drill bit touches the rock; When opening the hole, first quietly let the drilling rig drive, when the drill rod is in place in the rock, it is allocated to the full open position.
(2) Before starting the drilling rig, check whether the charging pressure of the accumulator is normal; Check whether the scouring water pressure and the lubricating air pressure can be; Check whether there is sufficient lubricating oil in the lubricator, and whether the oil supply is appropriate; Check the reverse tendency of the oil pump motor. (3) If the drilling rig cannot open the hole smoothly, it should first assign the rock drill to retreat, and then let the rock drill move forward to open the hole from the beginning.
(4) When replacing the drill bit, the drill bit should be gently pressed against the rock, so that the motor of the drill can be reversed to complete the sensitive unloading head.
(5) The inspection of hydraulic components can only be prevented under the condition of pole cleaning, and after the connecting tissue is removed, it must be quickly plugged with the cleaning tightly matched plug. Before the repaired rock drill is used from scratch, it is necessary to circulate the hydraulic oil into the oil circuit to wash the components of the hydraulic system.
(6) The oil level and oil supply of the lubricator should be checked regularly; The gear with reverse structure is regularly filled with high-temperature grease; Check the oil level in the lubricating oil tank regularly and remove the dirt in the oil tank
(1) When using the drilling rig to drill, the driver should be placed in the drilling position, so that the front end is against the rock, and the distribution should be careful to let the drilling rig move forward, so that the drill bit touches the rock; When opening the hole, first quietly let the drilling rig drive, when the drill rod is in place in the rock, it is allocated to the full open position.
(2) Before starting the drilling rig, check whether the charging pressure of the accumulator is normal; Check whether the scouring water pressure and the lubricating air pressure can be; Check whether there is sufficient lubricating oil in the lubricator, and whether the oil supply is appropriate; Check the reverse tendency of the oil pump motor. (3) If the drilling rig cannot open the hole smoothly, it should first assign the rock drill to retreat, and then let the rock drill move forward to open the hole from the beginning.
(4) When replacing the drill bit, the drill bit should be gently pressed against the rock, so that the motor of the drill can be reversed to complete the sensitive unloading head.
(5) The inspection of hydraulic components can only be prevented under the condition of pole cleaning, and after the connecting tissue is removed, it must be quickly plugged with the cleaning tightly matched plug. Before the repaired rock drill is used from scratch, it is necessary to circulate the hydraulic oil into the oil circuit to wash the components of the hydraulic system.
(6) The oil level and oil supply of the lubricator should be checked regularly; The gear with reverse structure is regularly filled with high-temperature grease; Check the oil level in the lubricating oil tank regularly and remove the dirt in the oil tank
The applications of mining slurry pumps are diverse. Their primary function is to transfer slurries from the point of extraction to processing facilities. In this stage, the slurry contains valuable minerals that need to be refined and extracted. Slurry pumps are also crucial in the dewatering process, where the goal is to remove excess water from extracted materials. This not only improves the efficiency of material handling but also protects the environment by reducing the risk of contaminated water discharge.
bombas de lodo minero

The wear pattern of jaws can also influence how effectively they crush materials. Manganese jaw plates tend to develop specific wear profiles, which can aid in maintaining a consistent output size. This is highly beneficial for maintaining product quality and ensuring that crushed materials meet industry specifications.
Une barre de forage est un long tube en acier qui est utilisé pour transférer la rotation et le couple du moteur de forage au bit de forage. La barre de forage est généralement conique à une extrémité, ce qui lui permet de se connecter à d'autres barres ou à un bit de forage. Les barres de forage sont disponibles dans une variété de tailles et de configurations, en fonction des exigences spécifiques du projet de forage.
Before delving into calculations, it's key to understand how a mud pump operates. Most modern drilling rigs use either triplex or duplex pumps, which use a series of pistons to create pressure. The fluid is drawn into the pump from a storage tank and pumped down the drill string. After reaching the drill bit, the mud carries cuttings back up to the surface through the annulus (the space between the drill string and the wellbore).
Cleaning method:
Open valve or desilting
Improved design of suction lines or desilting
Lower mounting height
Open valve or desilting
Improved design of suction lines or desilting
Lower mounting height